Geology framework agreement - Terna ATI CITIEMME (TO) e SONDEDILE (TE)

  • s1-c.1.jpg
  • pages-from-re22260b3b1945742-relaz-geot-caratterizzazione-r0-07.08.2020.jpg
  • spt.jpg
  • grafici-2.jpg

Framework Agreement for specialized activities and geological, geotechnical, hydrogeological, hydraulic and chemical/physical investigations preparatory to the feasibility design phase and to support the work phase.

PROJECT DESCRIPTION

The Framework Agreement concerns lot 6, an area that TERNA has defined to include projects for the regions of Trentino Alto Adige, Veneto, Friuli Venezia Giulia, Emilia Romagna and Tuscany.

Performance consists of SOA OS 20B “Geognostic Surveys”, such as Geognostic Surveys, Geotechnical Sampling in Surveys, Standard Penetration Test - Geotechnical Testing in Borehole Survey, Open Tube Piezometer Installation in Boreholes, Static penetrometric tests of mechanical (CPT) and electrical (CPTE), Static penetrometric tests of electric with piezocone (CPTU), Dynamic penetrometric tests DPSH (SCPT), Seismic prospections, Geotechnical tests and soil and seismic refraction samples - Laboratory geomechanic tomography, Tests on environmental investigations.

Services were carried out for final and executive feasibility projects such as Geological Report, Geotechnical Report, Hydraulic Report, Geomorphological Compatibility Report, Hydrogeological Compatibility Report, Preliminary Investigation Report for the management of excavation land and rocks in the feasibility design phase (Due Diligence/ Preliminary Use Plan/ Use Plan) and Sampling plans and final drafting for the design phase (Land and Rock Management Plan/Use Plan/Characterization Plan).

SPECIFICITY OF THE STUDY

Below there are some works studied:

- New 132 kV Electrical Sorting Station in Montecchio Maggiore (VI) and Connections to the 132 kV Sovizzo - Montecchio line (2022)
- Reorganization of the National Electricity Net in the area between Colunga and Ferrara (2022)
- 30 kv power line interference resolution - Villanova - Gissi (2021)
- 132 kV power line Agna-Ca Tron Lot 2 - Extraordinary maintenance (2021)
- Line 132 kV Rovigo RT - Ferrara RT - Lot 2 - Extraordinary maintenance (2021)
- Upgrading of the NTG in Val di Isarco by BBT connection (2021).
- Line 132 Kv “Montegalda - Padova RT” Extraordinary Maintenance (2020);
- Power line maintenance in the section between the supports nr. 1-18 - Line 132kv “Pontremoli - Edison Teglia” (2020);
- Linea132 kV in double tern: “Martignone - Battiferro” No. 737/758 - Burial of a section of the existing overhead power line - Zone 5.3 Bertalia - Lazzaretto in the Municipality of Bologna (2020);
- 132 kV line “Rovigo RT - Ferrara RT” (2020);
- 132 kV n.523 “Pisa Porta a Mare - Agip Sectioning” - Underground cable variant between supports nr 41 and 43 (2019);
- Construction of the new 132 Kv section of the T.712 E T.128 Line (2018).