- ClientTERNA
- Year 2018 - on going
- Sectors Energy Infrastructures
- Services - Noise Studies and Mitigation plans
- Air Quality Studies and Remediation plans
- Execution and Management of Monitoring Activities
- Environmental projects for Construction Sites
Overhead power line 150 kV in double circuit "SE Troia - Celle San Vito"
DESCRIPTION OF THE PROJECT
The aim of the work is to improve the reliability and safety of the 150 kV network characterized by significant power transits generated by the introduction into the network of the electricity produced by various renewable energy plants present and envisaged in the area between the Regions Puglia and Campania and in the area close to the city of Foggia. Therefore, two new 150 kV power connections will be developed, “S.E. Troia - Celle San Vito “and” S.E. Troia - Faeto “.
STUDY SPECIFICITY
Following the environmental compatibility decree (DM0000021 of 25th January 2018) of the 150 kV double-circuit overhead power line project Troia power station - Celle San Vito / Faeto power station, the phase of compliance with the requirements of the Ministry of the Environment and Ministry of Cultural Heritage was launched.
The prescriptions concern the following issues:
· Study of noise emissions · Study of atmospheric emissions during construction site · Project for restoration of construction site areas · Historical-botanical study · Masking project for power stations · Photo insertions · Study of compensation measures · Update of the Environmental Monitoring Plan · Environmental monitoring