Project Details
Client:
ENEL
Location:
Puglia
Project date:
1994-1995
Sectors:
Related service:
State of activity:
Approved by Ministry of Environment - Decree n.2475 of 15/06/1996
Project Details
PROJECT DESCRIPTION
VDP was selected to carry out the Environmental Impact Study required by the authorization procedures regarding the 380 kV Taranto-Galatina Power Line.
Therefore the environmental framework, the design phase and the non-technical project summary were set according to Law provisions (DPCM 27.12 / 88).
It is important to recall the following stages of the study: