- ClientENEL
- Year 1994-1995
- Sectors Energy Infrastructures
- Services Environmental Impact Assessment (EIA)
- Stage of Activity Approved by Ministry of Environment - Decree n.2475 of 15/06/1996
Environmental impact study for the 380-kV Taranto Galatina Transmission Power Line
PROJECT DESCRIPTION
VDP was selected to carry out the Environmental Impact Study required by the authorization procedures regarding the 380 kV Taranto-Galatina Power Line.
Therefore the environmental framework, the design phase and the non-technical project summary were set according to Law provisions (DPCM 27.12 / 88).
It is important to recall the following stages of the study:
- Comprehensive collection of already-available environmental and territorial data;
- Gathering of further relevant elements through on-site surveys and measurements;
- Evaluation of the work effects on the individual environmental components and on the overall environmental system;
- Preparation of the inclusive report and of the non-technical summary both dedicated to public engagement and information;
- Technical assistance comprising additional documentation at the appraisal stage.